Paper mock-ups before anything is made

Why every sign we design spends two weeks taped to a wall as a paper print before it goes to a fabricator.

A green safety sign with pictograms and a white arrow pointing left

Before the East Fork library reopened, we printed all 146 signs on paper at full size and taped them up for two weeks. Staff wrote on them in marker.

Twenty-three moved, six were cut and four were added. Each of those changes would have cost a fabricated sign, a fixing and a patched wall if we had found it after installation.

What paper catches

  • Signs placed where a door opens over them.
  • Text too small to read from where people actually stand.
  • Arrows that point the right way on the plan and the wrong way in the room.

What paper misses

Paper does not show glare from a window or how a material ages, so we still order one sample of every finished sign type and hang it on site for a week.